Freight is often 5–15% of the delivered cost of power equipment, and getting the container type wrong can double it. This is how we plan shipments.
Recent quotes from Shanghai or Qingdao, per container, US$: Durban about 5,100 (20 ft) / 6,500 (40 ft HC); Mombasa about 3,700 / 5,500; Jebel Ali about 7,800 / 8,800; Jeddah about 6,800 / 9,500; Chittagong about 2,850 / 3,350. Rates change weekly; add origin charges, insurance and destination charges. Our instant estimate uses these figures.
Roughly 25–35 days to East and South Africa, 20–30 days to the Gulf, 30–45 days to West Africa, plus customs at both ends.
Tell us the destination early: some countries require the inspection before the goods leave China.